by
James B. Atkins, FAIA, and Grant A. Simpson, FAIA
It may surprise some people to hear that the architect’s documents
cannot be used for construction. Many are of the opinion that the architect
prepares the documents and gives them to the contractor, and the contractor
takes them and builds the building from the information contained therein.
But nothing could be farther from the truth.
Then
why does the architect place on the documents “Issued for
Construction”? Although common practice, this phrase, when affixed
to the architect’s drawings, can be misunderstood. Nevertheless,
this phrase is better than labeling them “100% CD Set,” “Final
Construction Documents,” or something equally misleading. The documents
are not issued for construction per se, but instead, they are issued
to facilitate construction by expressing the design concept. The documents
do not contain sufficient information to construct the project, and much
more information is required before the work can be done.
In fact, the architect’s documents only represent information
sufficient for the contractor to begin “the contractor’s
required work,” which includes the preparation of detailed construction
documents, more commonly known as shop drawings and submittals, coordination
drawings, and alternate sketches, all of which set out the specific and
final details required for procuring and placing the finished work. By
contrast, drawings by architects merely reflect the finished design of
the work.
This article will examine the role contractor-provided construction
documents play in the construction process, along with the other information
that is required to complete a project. It will examine why the design
professional’s documents cannot be used as the actual documents
for implementing construction, and it will explore what information is
actually used, why it is used, and from where it originates.
The architect’s design is a concept
As defined by Webster’s, the term “concept” is “an
abstract or generic idea.” This definition makes it clear that
a concept is not a specific or finite solution with tangible parameters.
The limited content of the architect’s drawings is more explicitly
addressed in The Architect’s Handbook of Professional Practice, 13th Ed., in Section 13.4, “Construction Documents Production,” wherein
it states: “It is important that all parties understand that construction
documents are not intended to be a complete set of instructions on how
to construct a building. Construction means, methods, techniques, sequences,
procedures, and site safety precautions are customarily assigned as responsibilities
of the contractor to give the contractor full latitude in preparing bids
and carrying out the construction phase.”
Similarly,
Section 3.12.4 of AIA document A201, General
Conditions of the Contract for Construction states that the
inherently conceptual nature of construction documents prepared by
architects and the related responsibilities of the contractor/construction
manager for detailed submittals and shop drawings: “Shop Drawings,
Product Data, Samples and similar submittals are not contract documents.
The purpose of their submittal is to demonstrate for those portions
of the work for which submittals are required by the contract documents
the way by which the contractor proposes to conform to the information
given and the design concept expressed in the contract documents.”
Moreover,
Section 3.12.6 of A201 addresses the relationship of the contractor’s
submittals and shop drawings to the contractor’s plan for procuring
and placing the work: “By approving and submitting Shop Drawings,
Product Data, Samples, and similar submittals, the Contractor represents
that the Contractor has determined and verified materials, field measurements,
and field construction criteria related thereto, or will do so, and has
checked and coordinated the information contained within such submittals
with the requirements of the Work and of the Contract Documents.”
This powerful language explicitly requires the contractor to first check
each submittal and coordinate it with field conditions and the requirements
of the work before submitting it to the architect or engineer to review
for conformance with “the information given and the design concept
expressed in the contract documents.” MasterSpec, a product of
the AIA and the industry standard for construction specifications, devotes
an entire section on project management and coordination (Section 01310, “Project
Management and Coordination”). This description of the content
of coordination drawings explicitly requires them to be original, detailed
comparisons of the various trades, and it recognizes that the architect’s
drawings will likely be in conflict with selected equipment and required
clearances to the extent that coordination is necessary and advisable.
The contractor is specifically directed to provide sketches for resolution
of such predictable conflicts.
Furthermore, A201 places the contractor in charge of determining how
the work will be divided into separate trades, how the work will be bid
and purchased, how the purchased products and systems will be coordinated
and incorporated into the completed work, and that the work will be in
conformance with the design concept expressed in the contract documents.
When an RFI is not a change order
Although AIA document A201 makes the lines of responsibility for planning
the implementation of the work abundantly clear, and MasterSpec sets
out specific requirements for accomplishing the task, some assert that
a contractor’s change order is justified whenever information
is not specifically expressed in the architect’s documents. As
a result, contractors routinely make these assertions through the RFI
process and inevitably write change orders to add information to the
architect’s documents—information never rightfully required
or intended to be there in the first place.
For example, an architect has indicated “recessed fire extinguisher
cabinet” on an interior wall elevation in the architectural drawings.
While no specific dimensions are indicated for the cabinet location,
the specifications list several acceptable manufacturers for the cabinet.
Still, the contractor submits an RFI: “Please provide detail for
cabinet framing in wall.”
In
this instance, the contractor should provide the final answer since the
size and mounting detail of a recessed fire extinguisher cabinet varies
with the manufacturer. The architect could not have precisely detailed
the installation without knowing which manufacturer’s
cabinet was to be used. Also, it is not necessary for the architect to
provide a framing detail because the manufacturer’s literature
describes how the cabinet is to be installed. If the architect answers
the RFI with a framing detail, it is likely that the contractor will
ask for additional money for the newly detailed framing, alleging that
scope was added to the drawings. If the architect doesn’t answer
the RFI he or she risks being accused of not being responsive. One appropriate
response is to suggest that the contractor honor the manufacturer’s
instructions for the selected product.
Benefits of conceptual design drawings
AIA documents have expressly indicated for many years that the architect’s
drawings are conceptual, and they have required contractors to represent
through their review of shop drawings that they have “determined
and verified materials, field measurements, and field construction criteria.” These
actions naturally preclude “scaling” the design drawing directly
by attempting to determine dimensions from the drawings with the use
of an architect’s ruler.
In the 1980s, Gyo Obata, FAIA, one of the founding partners of Hellmuth,
Obata + Kassabaum Architects (HOK), decided to produce construction
drawings in freehand, thus emphasizing their conceptual nature. This
forced the contractors to rely on their work plan and the skills of their
trades to produce shop drawings to demonstrate how they intended to “conform
to the information given and the design concept expressed in the contract
documents.”
Although
considered by some to be extreme at the time, Obata did not remove any
usable information from his documents. He merely added a human factor
to his line work that expressed the information in its simplest and most
obvious form, while at the same time underscoring the reality that the
architect’s documents are conceptual. By contrast,
today’s computerized document production does little to reinforce
the conceptual nature of design drawings. While computers bring a high
level of consistency and efficiency to the architect’s work, design
drawings rendered via computer are so crisp and precise as to appear
to have the precision of a shop drawing.
As is obvious to most architects, there are many benefits to the use
of conceptual design drawings in the construction process. Some of these
benefits are that it:
- Promotes competition. Multiple acceptable manufacturers
allow the contractor to obtain the best price or best delivery schedule.
It is generally acknowledged that a single-source specified product will
be more expensive because of the lack of competition, and that is why
it is unlawful on public projects in many states.
- Provides for the latest
technology. A manufacturer’s product
may undergo model and specification changes after the project is designed
and before the work is installed. A good example is radiology equipment,
where specifications and features change almost monthly, and medical technologists
and radiologists desire the latest model for their facility. The architect’s
conceptual design allows for product procurement with more recent upgrades
and developments.
- Allows the trade to determine the final configuration.
While architects have a general familiarity with many products, the
trade contractor is the expert, knows the product best, and is more
capable of determining its ultimate design configuration.
- Places responsibility
for means and methods with an experienced provider. Much like the designer’s
expertise that is accrued from years of experience, the contractor’s
expertise in the latest construction techniques and how products and
buildings go together is a career endeavor. The contractor knows best
how to develop a plan for making the design concept a built reality.
The contractor’s plan
is critical
The contractor’s plan for procuring and placing the work is not
always entirely visible to the project team. Although the contractor
is required by the construction contract to submit shop drawings, produce
coordination drawings, provide sketches to resolve dimensional conflicts,
and hold pre-installation conferences—all of which the architect
should be aware of and may attend—for the most part, the contractor’s
work plan is transparent.
Components of the contractor’s plan for the work are addressed
in Guidelines for a Successful Construction
Project, a joint publication
of The Associated General Contractors of America, the American Subcontractors
Association, and the American Specialty Contractors. Pre-installation
conferences and coordination of subcontractors are addressed in Section
D.2.a (“Guideline on Communications”): “Coordination
should be assured through regular on-the-job meetings of the general
contractor’s authorized project representative and the on-site
subcontractors’ authorized project representatives. Additional
meetings may be required for subcontractors whose work might interfere
with another at a given time.”
This publication—formerly known as the Construction Industry Survival
Kit—also includes shop drawings and submittal data and coordination
drawings as primary topics for discussion during the pre-construction
conference. In Section 6.1 (“Guideline on Preconstruction Conferences”),
under Topics for Discussion, is Item 4: “Shop drawing and sample
submittal data including procedures for submittal, review, and approval
. . . ” Item 5 mentions coordination drawings, which are referred
to as interference and composite drawings: “Requirements, if any, for interference
and/or composite drawings. Who initiates them and what will be the order
of progression of these drawings; what is the impact on time for performing
the work if composite drawings are required?”
Through such publications, these major construction trade associations
acknowledge the role of the contractor in developing and managing the
work of coordinating the subcontractors and providing composite coordination
drawings. They also recognize that time and planning will be required
to coordinate the subcontractors and prepare the drawings necessary to
facilitate constructing the work.
The contractor’s plan is critical to the success of a project,
and it is developed and implemented by the contractor’s staff.
Yet contractors sometimes reduce staff as they seek to control general
conditions costs or because of pressure from owners to reduce expenses.
Owners often view these temporary facilities and services as transient,
with no sustaining benefit to the project. However, efforts to reduce
these costs can be misguided and may adversely affect the project. Staff
reductions are not made because planning the work is not required, and
consequently the work must be provided by an alternate source. For survey
and layout services, a common practice today is to buy layout work from
the individual trades performing the work. For example, the plumber may
be contracted to measure and lay out the locations of plumbing fixtures
and equipment, and the drywall contractor may be contracted to measure
and lay out the walls.
Under
this scenario, where layout is not provided as a general conditions service,
the ability of the contractor to confirm that the plumber’s
layouts are compatible with the drywall contractor’s layouts is
reduced. Typically, there are issues of coordination that must be worked
through between the two subcontractors. Since the layout process has
essentially bypassed the contractor’s supervision and control,
it is not a part of the work plan, and the subcontractor’s source
for layout information apparently becomes only the architect’s
drawings. Consequently, if there is a problem with coordinating the layout
between the subcontractors, the architect is often mistakenly viewed
as the responsible party.
The contractor is responsible for subcontractors’ work
According to Section 3.3.2 of AIA document A201, the general contractor
is solely responsible for the acts of subcontractors and the coordination
of their work: “The Contractor shall be solely responsible for
and have control over construction means, methods, techniques, sequences,
and procedures and for coordinating all portions of the Work under
the Contract . . . ”
Coordination of the subcontractors by the contractor is contractually
required, and it is necessary for producing properly placed work. Attempting
to transfer the responsibility for coordinating the work to the architect
is in conflict with the general conditions, the recommendations of the
leading trade associations, and, although it may be a common occurrence,
it is not good construction practice.
The
issue of pressuring contractors to reduce their general conditions costs
has seemingly played a part in causing layout and coordination of the
work by the contractors in the field to become a vanishing art. The act
of developing a work plan, working with and coordinating subcontractors,
and answering their questions has instead evolved into an intensive RFI
exchange often designed to force the architect to provide some or all
of the contractor’s field coordination services under duress. This
act of conscripting the architect or engineer is inherently unsuccessful
because they do not possess the contractor’s skills or contractual
authority, and they do not provide supervision. In the construction process,
there is simply no substitute for the contractor’s work plan.
The following RFI reflects the occasional passive nature of how a contractor
might attempt to conscript the services of an architect: “Embeds
for the roof screen wall support column bases were set per unapproved
shop drawings in the interest of schedule. Please provide a detail for
attaching the column base plates with drilled epoxy inserts.”
The contractor should have engaged an engineer to design a correction
to this placement mistake and proposed an alternate sketch for the engineer
of record to review as MasterSpec requires. Nevertheless, the design
team, in an effort to assist in resolving the problem, responded by sending
an Architect’s Supplemental Instruction (ASI) with a detail for
the inserts as requested. At the end of the project, adding insult to
injury, the contractor submitted additional costs in a change order request
for “providing inserts per the architect’s revised detail” that
was attached to the ASI, alleging that the detail was not the most cost-effective
solution.
Systems may be conceptually equal but nominally different
Both the architect’s drawings and the contractor’s procurement
and placement plan, which includes submittals and shop drawings, are
affected by the proprietary nature of the specific materials and systems
that the contractor decides to purchase. In the absence of a sole-source
specification, the architect cannot be expected to know exactly which
suppliers, manufacturers, or subcontractors the contractor will select
to include in the project. The proprietary nature of today’s market
dictates that one vendor’s product will not exactly match another
vendor’s product. Thus, the architect details the concept of an
installation and specifies the products or systems advertised or known
to be conceptually equal in quality. The contractor is responsible for
determining and defining specifically how the conceptually equal but
nominally different products or systems that have been chosen for use
in the project will be incorporated into the work.
An example of a conceptually equal but nominally different product can
be found in the case of two popular manufacturers of metal clad wood
windows. Both Pella and Andersen manufacture a wood window nominally
sized 3’ wide by 5’ high. However, the actual window provided
by Pella is 3’ 1” wide by 4’ 11” high, and the
window provided by Andersen is 2’ 11-1/2” wide by 4’ 11-1/2” high.
Although the windows are of slightly different sizes, the differences
do not invalidate the concept of a 3’ by 5’ window. Thus,
without advance knowledge of exactly which window the contractor will
propose to buy, the architect can approximately, but not exactly, represent
in the design documents what is required for the project. The subcontractor
then indicates in submitted shop drawing exactly how the selected window
will be incorporated into the work. The shop drawing, although it is
not a “contract document,” becomes the document that is actually
used for construction. The architect’s documents, since they are
conceptual, are not and cannot be the actual documents from which construction
is performed.
In another example, the conceptually equal but nominally different nature
of the final product to be provided is actually of little concern to
the architect, provided the contractor coordinates the work of the subcontractors.
RFI Question: Fire/smoke dampers have been approved as 120 volt. The
security system subcontractor has requested permission to change these
dampers to 24 volt. Will this change be acceptable?
Engineer’s Response: 120 volt or 24 volt is acceptable. Subcontractors
shall coordinate per contract.
As long as the dampers are coordinated and function with all related
systems, they will be in compliance with the design concept.
The contractor confirms the architect’s
dimensions
The purpose of the dimensions given in the architect’s drawings
is to define the limits of and provide guidance for placement of the
elements of the work. If there is a category of information provided
in an architect’s drawings that must be used directly during the
construction process, it is likely to be dimensional information. Nevertheless,
the architect’s dimensions must be thoroughly examined and verified
by the contractor preparing the plan for procuring and placing the work
because of the variables in available products and construction techniques.
Therefore, the dimensions provided by the architect are presented only
in support of the design concept. Column grids and building limits may
be presented and used literally as long as they have been confirmed by
the contractor’s surveyor. However, standard convention dictates
that the architect may use certain nominal dimensions that the contractor
must interpret in actual terms. For example, an 8” concrete masonry
unit is actually 7-5/8” tall, and a 2x4 wood framing member is
actually 1-1/2” by 3-1/2”.
Dimensions are also impacted by nominal proprietary differences as in
the case of the window size example given above, or in the case of small
differences in the actual dimensions of kitchen appliances, plumbing
fixtures and accessories, floor tile, elevators, and many other products.
These nominally differing dimensions, when they have a critical impact
on the layout of the building, must be highlighted in submittals, resolved
through the RFI process, or, in most cases, merely coordinated by the
contractor or subcontractor on site.
A good example of such a condition is pipe penetrations in the building
structural frame. The specifications often require “sleeve layout
drawings” to be submitted with the structural shop drawings. The
contractor is in the best position to determine specifically where the
sleeves for the piping can be placed so as to not interfere with critical
structural members such as reinforcing steel or post-tensioning tendons,
or with the contractor’s provisions for constructability. The architect
need not be concerned about the precise location of the sleeve as long
as it falls within a wall or chase and meets the requirements of the
design concept.
Convention and common sense also allows that some building elements
may simply be “conceptually indicated” but not actually dimensioned.
Building elements often indicated without dimensions commonly include
doors occurring in a long run of wall, electrical outlets whose specific
location is not critical, and other such elements. The final “nominal” location
of these building elements is rightfully left to the discretion of the
contractor.
How it is supposed to work
When things go the way they are supposed to, the architect’s interaction
is essentially one of answering questions about design intent and possibly
issuing a few supplemental instructions. The contractor significantly
marks up submittals, and pre-installation conferences are held at the
contractor’s request rather than having the meetings required in
the specifications. If all went as intended, a project would go something
like this:
- Architect designs project and issues design drawings (drawings
locate, specifications establish quality)
- Contractor develops plan for
procuring the work and allocates work among trades
- Contractor and trades
develop a plan for placing the work and prepare composite coordination
drawings and alternate sketches
- Trades prepare submittals and submit
to contractor
- Contractor coordinates trade submittals with the plan
for the work, marks up and approves submittals, and submits to
architect
- Architect reviews submittals for conformance with design concept
- Contractor and trades construct with approved submittals
- Contractor issues RFIs for questions that cannot be answered
from the information given or for questions about discrepancies in
the architect’s documents
- The architect responds to RFIs with answers to questions.
If a project was indeed constructed as the AIA documents anticipate,
there would be less paperwork, fewer meetings, and fewer conflicts and
disagreements. There may be higher general conditions costs to cover
the contractor’s necessary labor, but there would be fewer coordination
issues, fewer reimbursable expenses for the owner to pay, and a shorter
period to close out the project. Although the contractor’s plan
for procuring and placing the work is not a frequent topic of conversation
around the job site or in the project meeting, there are contractors
that actually prepare such a plan and execute it as the AIA and the leading
construction trade associations recommend. The telltale signs are marked-up
trade submittals, detailed coordination drawings, fewer RFIs, more installation
conferences, and less correspondence in general.
Architects conceive the concept, contractors plan the work
Contractor-provided construction documents are essential for constructing
a project, and it is evident that the architect’s drawings alone
cannot be used because they are conceptual in nature and inherently
inadequate for that purpose. If design drawings were sufficiently complete
and adequate for construction, there would be no need for the general
contractor. The architect would be providing the plan for putting the
work in place. The manufacturer and model along with the precise specifications
and physical characteristics of all products and systems in the building
would be known and detailed in the drawings in advance. In developing “a
complete set of instructions for building the building” the architect
would already have determined the means and methods for placing the
work. There would be no submittals because all data would be fully
anticipated and addressed in the contract documents. There would be
no RFIs, no ASIs, and much less correspondence overall. Moreover, project
costs would likely increase due to the absence of competition.
While the Building Information Model may improve the coordination process
in the future, the need for a contractor’s work plan will never
go away. Graphically illustrated concepts, desires, and intentions will
never precisely match constructed fact. By its very nature, the construction
process requires that someone plan, schedule, coordinate, and direct
the means and methods necessary for project construction and completion.
Architects will continue to design projects and produce conceptual drawings
for the contractor’s use. However, until the industry acknowledges
the need and demands that contractors plan and coordinate the work, architects
will continue to be expected to coordinate both the contractor and the
work of the trades. Until owners are enlightened as to the contractor’s
responsibilities under the AIA documents, the misguided expectation that
the architect is responsible for coordinating the work will remain. The
legal industry will continue to attempt to hold the architect’s
conceptual drawings to shop drawing standards, and the number of claims
against architects will continue to rise.
Copyright 2005 The American Institute of Architects.
All rights reserved. Home Page
|