Stored materials in Application for Payment




How does a Contractor bill for stored materials on an Application for Payment? Does the AIA publish an affidavit for stored materials?




Refer to AIA Document G703™–1992, Continuation Sheet. Materials presently stored but not yet incorporated into the work are listed separately in Column F.


Materials which continue to be stored in the following months pay periods should be listed Column F until the materials are incorporated into the work, at which time they are moved to Column E.


The Contractor's certification in the following documents includes any listed stored materials:


G702™–1992, Application and Certificate for Payment


G732™–2009 (formerly G702™CMa–1992), Application and Certificate for Payment, Construction Manager as Adviser Edition


G742™–2015, Application and Certificate for Payment for a Design-Build Project


The AIA does not publish a separate affidavit for stored materials.





AIA Version:

AIA Contract Documents Software - all versions



Last Updated:




Was this information helpful? Please e-mail comments to