Stored materials in Application for Payment

 

Question

 

How does a Contractor bill for stored materials on an Application for Payment? Does the AIA publish an affidavit for stored materials?

 

Answer

 

Refer to AIA Document G703™–1992, Continuation Sheet. Materials presently stored but not yet incorporated into the work are listed separately in Column F.

 

Materials which continue to be stored in the following months pay periods should be listed Column F until the materials are incorporated into the work, at which time they are moved to Column E.

 

The Contractor's certification in the following documents includes any listed stored materials:

 

G702™–1992, Application and Certificate for Payment;

 

G732™–2009 (formerly G702™CMa–1992), Application and Certificate for Payment, Construction Manager as Adviser Edition.

 

The AIA does not publish a separate affidavit for stored materials.

 

 

 

 

AIA Version:

AIA Contract Documents Software - all versions

Platform:

All

Last Updated:

2014-06-17

Number:

575

Was this information helpful? Please e-mail comments to docinfo@aia.org