Question

 

Do I need to use general conditions with AIA Document A102™–2007, Standard Form of Agreement Between Owner and Contractor Where the Basis for Payment Is the Cost of the Work Plus a Fee with a Negotiated Guaranteed Maximum Price? What general conditions are used with this agreement?

 

Answer

 

General conditions are an essential part of AIA Document A102™–2007 and must be attached to or incorporated into the agreement. This agreement is tailored to be used with the following general conditions:

 

A201™–2007, General Conditions of the Contract for Construction.

 

 

 

 