by John Curtin
Design professionals often are asked by an owner/client to assist in
obtaining the services of a contractor to build projects either through
a public bidding process or by invitation. Typically, owners want to
know how they can protect themselves in the event that a selected contractor
fails to satisfy the requirements for entering into the contract or does
not construct the project in accordance with the plans and specifications.
In general, the answer is to use bonds issued by a surety.
Sureties are a specialized segment of the insurance industry, with their
own set of procedures for performing their specific role. Sureties write
bonds that are three-party agreements between the surety, the project
owner, and the contractor on the project.
Although there are different types of bonds, each of which is written
to guarantee certain contractual obligations, they all serve to guarantee
the contractor’s duties to the owner—provided the owner fulfills
its obligations to the contractor. The most common forms of bonds used
in the construction industry are bid bonds, performance bonds, payment
bonds, maintenance bonds, supply bonds, and subcontractor bonds.
Bid bonds
Contractors who submit bids usually are asked to provide a bid bond.
The bid bond states that the contractor will enter into a contract
when one is offered and will provide bonding as required. Bid bonds
generally are written with a penalty equal to a percentage of the contract
price, usually 5, 10, or 20 percent. They may also be written with
a specific dollar penalty. If an owner offers a contract to a selected
contractor, and the contractor refuses to enter into the contract,
the owner may make a claim against the bid bond for the difference
between the price of the contract in question and the price of a substitute
contract or the penalty of the bid bond, whichever is less.
Although most surety companies file rates or fees for bid bonds, it
is unusual for a surety to require payment for issuing a bid bond, particularly
for customers who regularly produce bid bonds.
Performance bonds
Performance bonds guarantee to the owner that the contractor will perform
its contractual obligations in accordance with the plans and specifications.
These bonds can take a variety of forms, ranging from the very simple
to the long and complicated. There also are industry-standard forms
that are promulgated by such groups as the AIA, Engineers Joint Contract
Documents Committee, Associated General Contractors of America, and
Design-Build Institute of America.
Whatever language is used, the underlying assumption is that the owner
will perform its obligations to the contractor, and, therefore, the surety
is obligated to fulfill the duties of the contractor, if that contractor
is unable to do so.
The
cost of a performance bond usually is less than 1 percent of the contract
price. If the contract is under $1 million, however, the premium may
run between 1–2 percent. Bonds may be more costly, depending upon the
credit-worthiness of the contractor.
Labor and material payment bonds
Labor and material payment bonds are companions to the performance bond.
They assure the owner that the labor, material, and subcontractor costs
on the job will be paid. This assurance is for the use and benefit
of all laborers, material suppliers, and subcontractors who are eligible
by contract or statute for the protection afforded by the payment bonds.
They can also act as a way to protect the project from liens.
Because a performance bond nearly always is accompanied by labor and
material payment bonds, they typically are included in the performance
bond fee.
Maintenance bonds
Maintenance bonds are used when an owner wants a warranty period beyond
one year. A warranty period can be extended for an annual fee, but
sureties generally do not go beyond a total of two or three years.
The annual fee for a maintenance bond is a fraction of the cost of
a performance bond.
Supply bonds
Supply bonds guarantee that ordered materials will be delivered. Such
bonds generally are employed if an item is critical, time-sensitive,
hard to find, or proprietary. Supply bonds may guarantee only a purchase
order, so the terms and conditions of that order should always be carefully
drafted. The cost of these bonds is usually minimal.
Subcontractor bonds
Frequently, general contractors will require from their subcontractors
the same types of bonds required by the owner. Generals may do this,
for example, when the sub trade is critical to the project, the sub’s
price was much lower than its competitors, the sub is not well-known
to the general, or the general’s surety requires the bonding
of some or all subs as a precondition to bonding the general.
The bottom line is that the surety industry can go a long way to removing
much of the risk in bidder selection of the project not being completed
or that the contractor’s unpaid creditors will place a lien on
the project. Moreover, by reducing those risks, the owner may also reduce
the cost of borrowing money to finance the project.
Copyright 2005 The American Institute of Architects.
All rights reserved. Home Page
|