A
per-ton price increase at the mill level for structural steel of 56 percent
does not equate to increases in project costs of 56 percent. For a typical
project, the cost the total structural steel package (material, detailing,
fabrication, transportation, and erection) will represent 10 percent
to 12 percent of the total project cost. As a percentage of the steel
package, the mill material will typically represent 30 to 40
percent. This means that of total project cost, the structural steel
material will account for only 3 to 4 percent. An increase in mill product
costs of 56 percent will translate into an increase in project cost of
about 2 percent.
But the increase in the price of the steel package and overall project
costs are increasing more than 1.5 percent. The reason behind the higher
rates of increase is that there are other types of steel (plates, tubes,
and metal decking) often included in the steel package and that, as far
as the overall project is concerned, many other components are affected
by rising steel prices. When all of these (piping, sprinklers, elevators,
door frames, HVAC ductwork, reinforcing bar) are taken into account,
the anticipated increase in project cost for a steel-framed project is
3.6 percent per $100 increase in steel price.
In the past 12 months, steel (average of all types) has increased by
about $250 per ton. The resulting price increase on a steel-framed project
is in the neighborhood of 12 percent. Does this mean the value of using
steel in a project has decreased by 10 percent? No. Because of the amount
of steel still utilized in a concrete framed building for other building
and structural systems (often the amount of steel used to reinforce concrete
columns and beams can exceed 50 percent of the equivalent weight of a
steel beam or column) the average increase to project cost is estimated
to be 3.3 percent per $100/ton increase in steel price or resulting project
price increase of 8 percent. But this 8 percent does not take into account
recent increases in plywood forming costs and cement costs. When these
additional factors are taken into account, the cost differential between
steel and concrete construction disappears.
Copyright 2004 The American Institute of Architects.
All rights reserved. Home Page
|